Long-Term
REHABILITATION WORK
this is a long-term project,
where we will undertake projects to repair and rebuild some of the
basic needs infrastructure, such as schools, or hospitals etc.
Table: Summary of Things Done by FireFly Mission –
Cyclone Nargis Project
(as at 4 August 2008)
Long-Term Rehabilitation
-
Identified
7 schools (2 middle and 5 primary) for rebuilding – located in
villages at Bogale, Dedaye, Moulmeingyun & Pyapon townships.
-
To-date
one school rebuilding had been completed & the other is 70%
completed
-
Identified
2 rural clinics for rebuilding – located Taman village, Bogale
Township & Byingazee, Pyapon Township
Google Earth Satellite Views of Schools and
Clinics Identified for Reconstructions in Villages Located at
Bogale, Moulmeingyun, Pyapon and Dedaye Townships

Schools for Reconstructions:
Middle Schools
-
Nyein Oo, Moulmeingyun Township
- planned & budgeted
-
Taman, Bogale Township
- planned & budgeted
Primary Schools
-
Shauk Chaung, Moulmeingyun
Township - completed
-
Ta Pyay Chaung, Moulmeingyun
Township - as at 31-Jul about 70% completed
-
Upper Jyophyu, Moulmeingyun
Township - planned & budgeted
-
Gwaygune, Dedaye Township
- planned & budgeted
-
Kyon Thin, Pyapon Township
- planned & budgeted
Rural Clinics for Reconstructions:
-
Taman, Bogale Township
- planned & budgeted
-
Byingazee, Pyapon Township
- planned & budgeted

Cyclone Orphans Adoption Programme
about 20 children had been adopted & are currently placed at the
Maha Pyinnya Beikman, Parahita (Charitable) Monastery, Shwegyin,
Bago Division
in addition, 30 other orphans and children from very poor families
from the border areas are also homed under the same institution
They are looked after by Ven Dr U Aggasara and his team of
compassionate brother monks and able assistants
Plan to build 2 hostels to accommodate these children are being
worked out
details of children and adoption will be released
soon
|
|