Goh Kuan Seng
29 Oct 2026
Lotus Home Girls Hostel update
We are delighted to share another significant milestone in the construction of our Girls’ Hostel at Lotus Children’s Home.
Last Saturday (24th October 2026), under the supervision of our structural engineer, Ujjal Dewan, the roofing and flooring work progressed remarkably. The third-storey roofing on the first and second lines of pillars, the second-storey roofing on the second and third lines, and the first-storey floor on the fourth line of pillars were successfully completed.
This achievement would not have been possible without the continued generosity and support of Firefly Mission, whose commitment to our education project is helping us move closer to completing this much-needed hostel for our girls.